Dear,
As the same reply of Mr.Ujin
enter a data of a new pattern i.e: no.2 of woking hours only
as no.1 would be used for the network demands
then in the properties panel of the pump enter the patt. no. 2
then repeat the cycle with each pump
PUMP1 Patt. 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PUMP2 Patt. 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0
PUMP3 Patt. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
1 and 0 are indication for workink hours
Another Solution:
look in the user Guide page 38 and try to apply the rules to the pumps
don`t forget to send me the result working or not
Yours,
Ahmad Gado
Environmental / Civil Engineer
|