Is Option 1 or Option 13 best?

First time user. I am trying to model a very simple application. One dam (2.2 acre surface area) with two additional cross-sections below and very close (0.17 mile apart). A local municipality has requested this model.

The inflow is very small and the inflow hydrograph is 130 cfs (18 acre drainage basin). Is Option 1 or Option 13 the best to use in this situation?
Reply With Quote
  #2 (permalink)  
Old 04-29-2004, 12:44 PM
Administrator
 
Join Date: Aug 2001
Location: Madison, WI
Posts: 780
Re: Is Option 1 or Option 13 best?

I would recommend Option 1 if tailwater submergence at the downstream face of the dam is not an issue. Option 1 is a bit easier to set up and you get a Reservoir Depletion Table in the output.

Sincerely,

Chris E. Maeder, M.S., P.E.
Senior Technical Engineer
chris.maeder@bossintl.com
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are Off
[IMG] code is Off
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


All times are GMT. The time now is 02:44 AM.