Dear JMill:
Note that HEC-RAS 3.01 has now more strict checking of the bridge geometry. Therefore, we have implemented more strict checking of the HEC- RAS input data in RMS and RiverCAD.
If you add the "culvert length" and the "bridge rail to section distance" together, this total length must be less than the "channel flow length" defined at the next upstream cross-section (flow lengths are measured in a downstream direction). Otherwise, you will get an error, as you have reported.
I am fairly certain that if you review these numbers in your model, you will see what I am describing
Sincerely,
Chris E. Maeder, M.S.
Senior Technical Engineer
chris.maeder@bossintl.com